NTPC completes trial operation of Darlipali Unit 2 successfully

0
435
The trial operation of the second 800 MW unit of NTPC Darlipali in Sundergarh district of Odisha was successfully completed on July 21.
Trial operation involves running the unit for seventy – two hours continuously at full load to demonstrate the capability of the unit.
Installed capacity of NTPC Darlipali, Sundargarh is now 1,600MW.
With this, the total installed capacity of NTPC group has become 66,875 MW.